A batch of writ appeals was filed by guest faculty – Assistant Professors, Sports Officers and Librarians engaged after advertisement and selection and serving 10 to 30 years in…
16-Yrs Delay In Completing AIIMS Jodhpur Trauma Centre: Rajasthan HC Pulls Up State, Expresses Inclination To Impose ₹50 Crore Cost
Update / Judgement Date
15 Dec 2024
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
View Count
The Rajasthan High Court addressed delays in the construction of the AIIMS Jodhpur project, causing inconvenience to the state government. The Court intervened after the state raised concerns about the completion timeline and the consequences of the delays. The ruling underscored the importance of adhering to contractual agreements and timelines in public sector projects. The Court directed the responsible authorities to expedite the construction work and resolve any pending issues. This judgment aims to ensure that public infrastructure projects are completed on time, benefiting the citizens who rely on such services for their healthcare needs.