Karnataka RERA Directs Ozone Urbana Infra Developers To Refund Rs. 1.02 Crores To Homebuyer
Update / Judgement Date
04 Dec 2024
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
View Count
The Karnataka RERA directed Ozone Urbana Infra Developers to refund Rs 102 crores to a homebuyer due to delay in possession. The case involved a homebuyer who had been waiting for possession long past the agreed-upon date. RERA ruled that the builder’s failure to deliver the property on time constituted a breach of contractual obligations, and the consumer was entitled to a full refund. The decision highlights the consumer protection mechanisms under RERA, ensuring that developers are held accountable for delays in possession.