Deciding two connected writ petitions arising from a common Industrial Tribunal Award, the Delhi High Court set aside the Tribunal's direction granting hotel workmen a further…
Karnataka RERA Directs Ozone Urbana Infra Developers To Refund Rs. 1.08 Crores To Homebuyer For Delay
Karnataka RERA has directed Ozone Urbana Infra Developers to refund Rs. 10.8 crores to a homebuyer due to project delays. The authority found that the developer had failed to deliver the property within the promised timeframe without justifiable cause. The order includes interest payment on the refund amount to compensate for the delay. This ruling reinforces RERA's commitment to protecting homebuyers' interests and ensuring developer accountability. The decision sets a precedent for similar cases involving project delays and emphasizes the serious financial consequences developers may face for failing to meet their contractual obligations.