Possession Of Plot Offered Twice, HUDA Not Liable For Delay Caused Due To Road Shifting, Subsequent Plan Approval: NCDRC
The NCDRC (National Consumer Disputes Redressal Commission) held that HUDA (Haryana Urban Development Authority) was not liable for delays in offering possession of a plot that was offered twice, where the delay was caused by road shifting and subsequent plan approval. The commission acknowledged that the initial delay was due to factors beyond HUDA's control and that offering possession a second time after resolving the issues demonstrated their intent to fulfill their obligation.