Deciding two connected writ petitions arising from a common Industrial Tribunal Award, the Delhi High Court set aside the Tribunal's direction granting hotel workmen a further…
Failure To Make Timely Payments, MahaRERA Directs Homebuyer To Pay Rs. 1.18 Crore with Interest To Transcon Developers
In another ruling by MahaRERA, a homebuyer was directed to pay Rs 1.18 crore, along with interest, to Transcon Developers after failing to make timely payments as per the agreement. The homebuyer had entered into an agreement with the developer but delayed the payments, leading to a dispute. MahaRERA emphasized the need for buyers to adhere to their financial commitments and ruled in favor of the developer. The order demonstrates the regulatory body's balanced approach in addressing issues between developers and homebuyers. It also highlights the obligations of both parties under RERA, ensuring that contractual obligations are fulfilled to maintain transparency and fairness in property transactions.