An 85-year-old senior citizen sought eviction of his son and daughter-in-law from his self-acquired home under the Maintenance and Welfare of Parents and Senior Citizens Act,…
Haryana RERA Orders Shine Buildcon To Pay Interest To Complainant For Delayed Possession Of Shop
Update / Judgement Date
18 Jul 2024
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
View Count
In a recent ruling, the Haryana RERA directed Shine Buildcon to compensate a complainant for delayed possession of a shop, ordering interest payment at a rate of 10.75% per annum from the due date. The complainant, represented by legal counsel, successfully argued for compensation due to the significant delay in project completion. This decision underscores RERA's role in protecting consumer rights and ensuring timely possession under real estate agreements.