An 85-year-old senior citizen sought eviction of his son and daughter-in-law from his self-acquired home under the Maintenance and Welfare of Parents and Senior Citizens Act,…
Homebuyers Failed To Make Timely Payment, MahaRERA Orders Homebuyers To Pay Dues To Builder With Interest
Update / Judgement Date
17 Jul 2024
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
View Count
The Maharashtra Real Estate Regulatory Authority (MahaRERA) directed homebuyers to pay their outstanding dues with interest to Kapstone Constructions. The homebuyers had only paid 85% of the total amount for a flat in the Rustomjee Azziano Wing F project, despite the builder completing construction and obtaining the occupancy certificate. The authority found that the homebuyers violated the agreement terms and sections 19(6), 19(7), and 19(10) of the Real Estate (Regulation & Development) Act, 2016.