Procedural Red Tape And Bureaucratic Delays Inadmissible As Reasons For Condonation Of Delay: NCDRC
Update / Judgement Date
04 Jun 2024
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
View Count
2
The National Consumer Disputes Redressal Commission, chaired by Dr. Inder Jit Singh, rejected Hubli Electricity Company's appeal due to a 341-day delay. The company sought condonation citing bureaucratic delays, which the Commission deemed insufficient. \r
Citing precedent, including Office of the Chief Post Master General & Ors. vs. Living Media India Ltd. & Anr., the Commission held that administrative delays are not valid excuses, emphasizing that each case must be judged individually. \r
Without satisfactory grounds, the Commission dismissed both the appeal and the condonation application, as they exceeded the limitation period.