Deciding two connected writ petitions arising from a common Industrial Tribunal Award, the Delhi High Court set aside the Tribunal's direction granting hotel workmen a further…
RERA impact: Homebuyer to get Rs 65 lakh compensation for delay of over 9 years in possession of a flat in
Update / Judgement Date
26 May 2025
Source
Author
Team — WCP Legal Desk
Reading Time
1 min read
Haryana Gurgaon RERA Impact: Homebuyer to Get ₹65 Lakh Compensation for Delay of Over 9 Years in Possession of a Flat in Gurgaon The Haryana Real Estate Regulatory Authority (RERA) in Gurgaon has directed a developer to pay ₹65 lakh in compensation to a homebuyer due to a delay of over nine years in the possession of a flat. This ruling demonstrates the significant impact and effectiveness of RERA in protecting homebuyers' rights and holding developers accountable for project delays. It sends a strong message to real estate developers about the financial consequences of non-compliance with agreed-upon timelines.