The High Court of Delhi dismissed the petition seeking to challenge the arbitral award, affirming the rejection of multiple claims by the petitioner related to discrepancies and withheld payments in a construction contract. The court highlighted the lack of substantial evidence for the claims and reiterated the limited scope of interference in arbitration under Section 34 of the Arbitration and Conciliation Act, 1996.
Background
- Petitioner, S and S Construction Co., was awarded a tender for construction work valued at approximately Rs. 19.43 crores.
- Contract signed on 04.06.2010, with work to be completed within eight months; completion certificate issued on 17.12.2019.
- Disputes referred to arbitration; the arbitrator appointed on 19.04.2022.
- Of sixteen claims, seven were rejected; the petitioner challenged the rejection of claims regarding withheld amounts and damages.
Court’s Observations
- Petitioner failed to provide adequate evidence for claims, particularly regarding the unauthorized withholding of Rs. 13,00,000 and damages suffered.
- The court observed that pre-existing notices were provided before deductions, countering the claim that deductions were made without notice.
- Re-affirmation that interest charges on mobilization advances were valid under the contract.
- Claims for damages under Section 73 of the Contract Act were rejected due to a lack of proof of actual damages suffered due to price changes or prolonged contract durations.
- Emphasized the need for joint measurements between parties in support of claims, which the petitioner failed to demonstrate.
Legal Provisions Discussed
- Section 34 of the Arbitration and Conciliation Act, 1996.
- General Conditions of Contract (GCC) Clauses 2, 10B, 17.
- Section 73 of the Indian Contract Act, 1872.
Case Details
S AND S CONSTRUCTION CO vs. UNION OF INDIA THROUGH E E B F D II
Coram: HON'BLE MR. JUSTICE AVNEESH JHINGAN
Full Judgement / Attachment
Full Judgement